Client: WHP
Procurement, fabrication and installation of the following:
Steelwork-
-Fabrication and installation of 6No- free standing RRU/BOB frames complete with adjust support feet, each free-standing mount comes complete with 2No- 76.1 x 5 mm CHS poles x 800 mm high and weight plates
-Fabrication and installation of 1No- Self-closing gate to existing access ladder as measured on site
-Fabrication and installation of 4No- Step overs complete with bearing plates, concrete slabs & rubber to allow access over new cable tray
-Fabrication and installation of 2No- Large Step overs complete with bearing plates, concrete slabs & rubber
-Fabrication and installation of 2No- 203 x 203 x 46 UC new cabinet grillage steelwork members along with PFC to support the flooring
-Supply and install 45-metres non-slip matting x 900 mm wide
-Works based on CE Class 2.
Cable Tray Blocks-
-Removal of existing concrete blocks from existing tray and replacement with new rubber blocks only
-Removal of existing cable tray and concrete blocks and replacement with new 450 mm and 150 mm cable tray as below
-All waste lifted from rooftop by others with crane